Work Package
Detailed short-span tasks, or material items, identified by the performing contractor for accomplishing work required to complete a project. A work package represents a further breakdown of the work defined by the cost account. In traditional cost/schedule systems, the criteria for defining work packages is as follows: 1) Each work package is clearly distinguishable from all other work packages in the program. 2) Each work package has a scheduled start and finish date. 3) Each work package has an assigned budget that is time-phased over the duration of the work package. 4) Each work package either has a relatively short duration, or can be divided into a series of milestones whose status can be objectively measured. 5) Each work package has a schedule that is integrated with higher-level schedules.