Start Float
Start float is the amount of excess time an activity has between its Early Start and Late Start dates.
Source
Start-to-start lag is the minimum amount of time that must pass between the start of one activity and the start of its successor(s). This may be expressed in terms of duration or percentage.
Source
Starting Activity
A starting activity has no predecessors. It does not have to wait for any other activity to start. Many PM software packages permit multiple start activities if needed.