Expand your PMP skill-set by enrolling in one of our professional training courses today. Our 21 learning modules and 5 full-length practice tests will give you the confidence you need to suceeed.
Re-Profiling
In resource scheduling it is possible to indicate that the specified resource requirement profile may be modified to fit the availability, without changing the total amount required.
Source
Readiness Assessment
A meeting or series of meetings by selected members of the customer C/SCSC review team at a contractor’s plant, to review contractor plans and progress in implementing C/SCSC in preparation for a full demonstration review.
Source
Recurring Costs
Expenditures against specific tasks that would occur on a repetitive basis. Examples are sustaining engineering, production of operational equipment, tool maintenance, etc.
Source
Relationship
A logical connection between two activities.
Source
Relationship Float
Relationship free float is the amount by which the lag on that relationship would have to be increased in order to delay the successor activity. Relationship total float is the amount by which it would have to be increased in order to cause a delay in the completion of the project as a whole (or the violation of a late target).
Source
Remaining Duration
Time needed to complete the remainder of an activity or project.
Source
Replanning
Actions performed for any remaining effort within project scope. Often the cost and/or schedule variances are zeroed out at this time for history items.
Source
Report Specification File
A set of codified instructions, which defines the layout of a report.
Source
Request for Change
A proposal by the project manager for a change to the project as a result of a project issue report.
Source
Request for Proposal (RFP)
A bid document used to solicit proposals from prospective sellers of products or services.
Source
Request for Quotation
Equivalent to a Request for Proposal but with more specific application areas.
Source
Requirements
A negotiated set of measurable customer wants and needs.
Source
Residue File
A file in the same format as the resource availability file containing a specification of the resources remaining after a project is scheduled.
Source
Resource
An item required to accomplish an activity. Resources can be people, equipment, facilities, funding or anything else needed to perform the work of a project.
Source
Resource Analysis
A term for resource leveling and resource smoothing.
Source
Resource Assignment
The work on an activity related to a specific resource.
Source
Resource Availability
The level of availability of a resource, which may vary over time.
Source
Resource Breakdown Structure
A feature of hierarchical resources that facilitates both roll-up reporting and summary resource scheduling by enabling you to schedule at the detailed requirements level, and roll up both requirements and availabilities to a higher level.
Source
Resource Calendar
A calendar that defines the working and non-working patterns for specific resources.
Source
Resource Driven Task Durations
Task durations that are driven by the need for scarce resources.
Source
Resource Histogram
A view of project data in which resource requirements, usage, and availabilities are shown against a time scale.
Source
Resource Level
A specified level of resource units required by an activity per time unit.
Source
Resource Leveling
The resource scheduling process of determining scheduled dates such that neither the project completion date nor any target finishes are jeopardized while minimizing the maximum extent to which any resource availability is exceeded.
Source
Resource Offset
In the definition of resource requirements, the number of work periods between the start of the activity and when the resource is first required.
Source
Resource Optimization
A term for resource leveling and resource smoothing.
Source
Resource Period
In the definition of a resource requirement, the number of work periods for which a resource is required.
Source
Resource Planning
Evaluating what resources are needed to complete a project and determining the quantity needed.
Source
Resource Pool
A higher level resource in a resource breakdown structure.
Source
Resource Profile
The multiple specification of a single resource requirement or availability to indicate a variation over a period of time.
Source
Resource Requirement
The requirement for a particular resource by a particular activity.
Source
Resource Scheduling
The process of calculating a set of scheduled dates that takes into account the resource requirements of each activity and the availability of these resources.
Source
Resource Scheduling
The process of determining dates on which activities should be performed in order to smooth the demand for resources, or to avoid exceeding stated constraints on these restraints. (See also, Resource Leveling, Time-Limited Resource Scheduling and Resource-Limited Resource Scheduling.)
Source
Resource Smoothing
The process of rescheduling activities such that the requirement for resources on the project do not exceed resource limits. In smoothing, as opposed to resource leveling, the project completion date may not be delayed. Activities may only be delayed within their float.
Source
Resource Thresholds
In resource-limited scheduling it is possible to specify that a particular resource may be exceeded, if necessary, by an amount not to exceed the specified threshold for that resource.
Source
Resource Total
A specified total of resource units required by an activity over a period of time.
Source
Resource-Limited Resource Scheduling
The production of scheduled dates in which the resource constraints are considered as absolute and project completion is delayed as necessary to avoid exceeding resource requirements.
Source
Resourcing Plan
Part of the definition statement stating how the program will be resource loaded and what supporting services, infrastructure and third party services are required.
Source
Responsibility Assignment Matrix (RAM)
The RAM correlates the work required by a Contract Work Breakdown Structure (CWBS) element to the functional organization responsible for accomplishing the assigned tasks. The responsibility assignment matrix is created by intersecting the CWBS with the program Organizational Breakdown Structure (OBS). This intersection identifies the cost account.
Source
A defined unit within the contractor’s organization structure which is assigned responsibility for accomplishing specific tasks, or cost accounts.
Source
Retainage
A part of payment withheld until the project is completed in order to ensure satisfactory performance completion of contract terms.
Source
Reviewers
Those responsible for ensuring a product is completed and fault free at a quality review.
Source
A technique designed to quantify the impact of uncertainty. Usually, but not necessarily, associated with the Monte Carlo Simulation technique.
Source
Risk Analysis Histogram
A view in which the results of risk analysis are displayed as vertical bars, S-curves, or tables against a date scale.
Source
Risk Avoidance
Planning activities to avoid risks that have been identified.
Source
Risk Event
A discrete occurrence that effects a project.
Source
Risk Identification
Determining which risk events will effect the project.
Source
Risk Management
The art and science of identifying and assessing the risk factors during a project and responding to them in the best interests of the project objectives.
Source
Risk Management Plan
Part of the program definition statement that contains a record of all the risks in the business environment, and to the program itself.
Source
Risk Matrix
A matrix with risks located in rows, and with impact and likelihood in columns.
Source
Risk Prioritizing
Ordering of risks according first to their risk value, and then by which risks need to be considered for risk reduction, risk avoidance, and risk transfer.
Source
Risk Quantification
Evaluating the probability of risk event effect and occurrence.
Source
Risk Ranking
Allocating a classification to the impact and likelihood of a risk.
Source
Risk Reduction
Action taken to reduce the likelihood and impact of a risk.
Source
Risk Register
A file that holds all information on identifying and managing a risk.
Source
Risk Response Control
Responding to changes in risk during a project.
Source
Risk Response Development
Developing a plan of action to enhance opportunities and decrease threats.
Source
Risk Transfer
A contractual arrangement between two parties for delivery and acceptance of a product where the liability for the costs of a risk is be transferred from one party to the other.
Source
Risk Value
The number obtained when numeric impact and likelihood values are multiplied.
Source
Risks
Risks are events that if they occur can jeopardize the successful completion of the project. Risks should be identified and assessed for probability of occurrence and impact on the project.
Source
Rubber Baselining
An attempt by a contractor to take far-term budget and move it into the current period, in an attempt to disguise cost problems. Approach will be to move budget, but without a corresponding value of work, to mask cost difficulties. It is an indicator of a likely cost overrun condition.
Source