Glossary of PM Terms
A  B  C  D  E  F  G  H  I  J  K  L  M  N  O  P  Q  R  S  T  U  V  W  X  Y  Z 
Online PMP Training

Expand your PMP skill-set by enrolling in one of our professional training courses today. Our 21 learning modules and 5 full-length practice tests will give you the confidence you need to suceeed.

Labor Rate Variances
Difference between planned labor rates and actual labor rates.
Source
Ladder
A sequence of parallel activities connected at their starts or finishes, or both.
Source
Lag
Lag is the time delay between the start or finish of an activity and the start or finish of its successor(s). See FINISH-TO-FINISH LAG, FINISH-TO-START LAG, and START-TO-START LAG.
Source
Late Dates
Calculated in the backward pass of time analysis, late dates are the latest dates on which an activity can start and finish.
Source
Late Event Date
Calculated from backward pass, it is the latest date an event can occur.
Source
Late Finish
Late Finish dates are defined as the latest dates by which an activity can finish to avoid causing delays in the project. Many PM software packages calculate late dates with a backward pass from the end of the project to the beginning. 
Source
Late Start
Late Start dates are defined as the latest dates by which an activity can start to avoid causing delays in the project. Many PM software packages calculate late dates with a backward pass from the end of the project to the beginning.
Source
Leadership
Getting others to follow direction.
Source
Level of Effort (LOE)
Work that does not result in a final product (such as liaison, coordination, follow-up, or other support activities) and which cannot be effectively associated with a definable end product process result. Level of effort is measured only in terms of resources actually consumed within a given time period.
Source
Leveling
See Resource Leveling.
Source
Life-Cycle Costing
When evaluating alternatives, Life-Cycle Costing is the concept of including acquisition, operating and disposal costs.
Source
Likelihood
Assessment of the probability that a risk will occur.
Source
Line Manager
The manager of any group that makes a product or performs a service.
Source
Logic
See Network Logic.
Source
Logic Diagram
See Project Network Diagram.
Source
Logic Link
See Dependency Links.
Source
Logic Loop
A circular sequence of dependency links between activities in a network.
Source
Logical Relationship
A logical relationship is based on the dependency between two project activities or between a project activity and a milestone.
Source
Loop
In networks, a set of symbols indicating that one or more activities are mutually dependent.
Source
Ad_02_900x120
A  B  C  D  E  F  G  H  I  J  K  L  M  N  O  P  Q  R  S  T  U  V  W  X  Y  Z