Hammocks
A hammock groups activities, milestones, or other hammocks together for reporting. A hammock's milestone number ranges from 95 to 99. This allows for five levels of summation. For example, two hammocks at the 95 level can be combined in a 96 level hammock. Any number of hammocks are allowed within the five levels for a project. Most PM software calculates the duration of a hammock from the early and late dates of the activities to which it is linked.