Expand your PMP skill-set by enrolling in one of our professional training courses today. Our 21 learning modules and 5 full-length practice tests will give you the confidence you need to suceeed.
Finish Date
The actual or estimated time associated with an activity’s completion.
Source
Finish Float
Finish float is the amount of excess time an activity has at its finish before a successor activity must start. This is the difference between the start date of the predecessor and the finish date of the current activity, using the early or late schedule. (Early and Late dates are not mixed.) This may be referred to as slack time. All floats are calculated when a project has its schedule computed.
Source
Finish-To-Finish Lag
The finish-to-finish lag is the minimum amount of time that must pass between the finish of one activity and the finish of its successor(s). All lags are calculated when a project has its schedule computed. Finish-to Finish lags are often used with Start-to-Start lags.
Source
Finish-To-Start Lag
The finish-to-start lag is the minimum amount of time that must pass between the finish of one activity and the start of its successor(s). The default finish-to-start lag is zero. All lags are calculated when a project has its schedule computed. In most cases, Finish-to-Start lags are not used with other lag types.
Source
Finishing Activity
A finishing activity is the last activity that must be completed before a project can be considered finished. This activity is not a predecessor to any other activity -- it has no successors. Many PM software packages allow for multiple finish activities.
Source