Glossary of PM Terms
A  B  C  D  E  F  G  H  I  J  K  L  M  N  O  P  Q  R  S  T  U  V  W  X  Y  Z 
Online PMP Training

Expand your PMP skill-set by enrolling in one of our professional training courses today. Our 21 learning modules and 5 full-length practice tests will give you the confidence you need to suceeed.

Dangle
An activity or network which has either no predecessors or no successors. If neither, referred to as an isolated activity.
Source
Data Type
The characteristic indicating whether a data item represents a number, date, character string, etc.
Source
Delaying Resource
In resource scheduling, inadequate availability of one or more resources may require that the completion of an activity be delayed beyond the date on which it could otherwise be completed.  The delaying resource is the first resource on an activity that causes the activity to be delayed.
Source
Delegating
The process by which authority and responsibility is distributed from Project Manager to subordinates.
Source
Deliverable
A report or product that must be completed and delivered to ensure satisfaction of contractual requirements.
Source
Delphi Technique
A process where a consensus view is reached by consultation with experts. Often used as an estimating technique.
Source
Dependencies
Dependencies are relationships between products or tasks. For example, one product may be made up of several other ‘dependent’ products or a task may not begin until a ‘dependent’ task is complete. See also logical relationship.
Source
Dependency Links
Different types of links connecting activities in a precedence network.
Source
Design and Development Phase
The time period in which production process and facility and production processes are developed and designed.
Source
Detailed Plans
See Detailed Resource Plan .
Source
Detailed Resource Plan
A plan implemented when it’s necessary to plan and control a certain major activity within a stage. The plan sets costs and resource usage that correspond to the detailed technical plan.
Source
Detailed Technical Plan
A plan a plan used to give a specific breakdown of major activities. It exists in all but the smallest projects.
Source
Deterministic Network
A network with no facilities to accommodate probabilistic dependencies. Precedence networks are said to be deterministic.
Source
Direct Costs
Those costs (labor, material, and other direct costs) that can be consistently related to work performed on a particular project. Direct costs are best contrasted with indirect costs that cannot be identified to a specific project.
Source
Discontinuous Activity
An activity in which the interval between the start and finish dates is allowed to exceed its duration in order to satisfy start-to-start and finish-to-finish relationships with other activities.
Source
Discontinuous Processing
This option assigns the discontinuous attribute to all activities for a time analysis session, except where overridden by a specific activity type.
Source
Discrete Effort
See Work Package.
Source
Discrete Milestone
A milestone that has a definite scheduled occurrence in time.
Source
Duration
Duration is the length of time needed to complete an activity.
Source
Duration Compression
Often resulting in an increase in cost, duration compression is the shortening of a project schedule without reducing the project scope.
Source
Ad_02_900x120
A  B  C  D  E  F  G  H  I  J  K  L  M  N  O  P  Q  R  S  T  U  V  W  X  Y  Z