Expand your PMP skill-set by enrolling in one of our professional training courses today. Our 21 learning modules and 5 full-length practice tests will give you the confidence you need to suceeed.
Acceptance
The formal process of accepting delivery of a product or a deliverable.
Source
Activity
The smallest self-contained unit of work used to define the logic of a project. In general, activities share the following characteristics: a definite duration, logic relationships to other activities in a project, use resources such as people, materials or facilities, and have an associated cost.
Source
Activity Definition
Identifying the specific activities that must be performed in order to produce project deliverables.
Source
Activity Duration
Activity duration specifies the length of time (hours, days, weeks, months) that it takes to complete an activity. This information is optional in the data entry of an activity. Work flow (predecessor relationships) can be defined before durations are assigned. Activities with zero durations are considered milestones (milestone value of 1 to 94) or hammocks (milestone value of 95 to 99).
Source
Activity Duration Estimating
Estimating the number of work periods that will be needed to complete the activity.
Source
Activity File
A file containing all data related to the definition of activities on a particular project.
Source
Activity ID
A unique code identifying each activity in a project.
Source
Activity Status
The state of completion of an activity. A planned activity has not yet started. A started activity is in progress. A finished activity is complete.
Source
Activity-on-Node
A network where activities are represented by a box or a node linked by dependencies. See also Precedence Diagram Method.
Source
The sum of costs actually incurred in accomplishing the work performed.
Source
Actual Dates
Actual dates are entered as the project progresses. These are the dates that activities really started and finished as opposed to planned or projected dates.
Source
Actual Direct Costs
Those costs specifically identified with a contract or project, based upon the contractor’s cost identification and accumulation system. See also Direct Costs.
Source
A resource that may be substituted as the requirement for an activity if the requested resource is not available.
Source
Approval to Proceed
Approval by the project board at initiation or prior to the beginning of the next stage.
Source
Archive Plan
A function of some computer programs that allows versions of a plan to be archived.
Source
Arrow Diagram Method (ADM)
One of two conventions used to represent an activity in a project. Also known as Activity-on-Arrow or i/j method.
Source
As-Late-As-Possible (ALAP)
An activity for which the application sets the early dates as late as possible without delaying the early dates of any successor.
Source
As-Soon-As-Possible (ASAP)
An activity for which the application sets the early dates to be as soon as possible. This is the default activity type in most project management systems.
Source
Any scope changed for which authorization to proceed has been given, but for which the estimated costs are not yet settled.
Source
Authorized Work
The effort which has been defined, plus that work for which authorization has been given, but for which defined contract costs have not been agreed upon.
Source